Highway 1: When was it built? 1949-61 & in Sections

Hwy1Hwy2

COAST HIGHWAY: BUILT IN SECTIONS, 1949-61

1. Farallone City—-Miramar

Plans Approved: 1949

Accepted: Feb. 2, 1950 (when completed)

2. Miramar-South of Frenchman’s Creek

Approved: November 1949

Accepted: September 1950

3. Frenchman’s Creek to Miramontes Point

Approved: January 1954

Accepted: March 1955

4. Miramar – Lobitos Creek Road

Approved: March, 1951

Accepted: May 1952

5. Lobitos – Martin’s Beach

Approved: April 1950

Accepted: June 1951

6. Martin’s Beach- 2 miles south of Tunitas

Approved: May 1942

No “as built date”

7. Tunitas Road

Rebuilt: May 1961