COAST HIGHWAY: BUILT IN SECTIONS, 1949-61
1. Farallone City—-Miramar
Plans Approved: 1949
Accepted: Feb. 2, 1950 (when completed)
2. Miramar-South of Frenchman’s Creek
Approved: November 1949
Accepted: September 1950
3. Frenchman’s Creek to Miramontes Point
Approved: January 1954
Accepted: March 1955
4. Miramar – Lobitos Creek Road
Approved: March, 1951
Accepted: May 1952
5. Lobitos – Martin’s Beach
Approved: April 1950
Accepted: June 1951
6. Martin’s Beach- 2 miles south of Tunitas
Approved: May 1942
No “as built date”
7. Tunitas Road
Rebuilt: May 1961